Dogger Bank Wind Farm — a joint venture between SSE Renewables, Equinor, and Vårgrønn, developed in three 1.2 GW phases — required 277 monopile foundations and transition pieces installed across a North Sea site 130 km off the Yorkshire coast, one of the most demanding wave environments any offshore wind foundation campaign has faced.
The commercial interest is less the scale than the sequencing: three consecutive phases requiring repeated vessel and equipment mobilisation under Seaway7's overall foundation-installation scope, running across three years, while a new transition-piece design was deployed in the field for the first time.
The split-level transition piece was designed specifically for safe technician access directly into the turbine tower from service and operations vessels — a decision made to reduce manual handling and lifting operations across the wind farm's roughly 35-year operational life, not just to simplify installation.
Three installation phases, three years, and a transition-piece design decided before a single foundation went in the water — made to save handling risk decades into the asset's operating life.
Dogger Bank's installation campaign is a case study in phased vessel, equipment, and subcontractor mobilisation at scale: Seaway7's tier-one foundation scope continued across all three sequential phases, with DEME subcontracted for opening foundation work at Dogger Bank A, while separately contracted heavy-lift campaigns installed the substations documented here — Saipem for Dogger Bank B, Heerema for Dogger Bank C.
For further reading, see Heavy Lift Engineering for Offshore Wind and Jacket Lift System Interfaces, which cover the foundation types used across this campaign.
Related case studies: Vindeby · Borssele · London Array
Sources: New Civil Engineer — turbine count, monopile foundations and HVDC substation programme; Offshore Wind — substation jacket dimensions and water depths. Figures are reported as published and reflect a project still under construction.