The four-legged jacket foundations standing beneath Borssele's offshore substations look calm today — repetitive, almost routine. But during load-out, transport, and upending, each jacket went through structural conditions it was never designed to see once in service.
While the Borssele wind turbines themselves stand on monopile foundations, the wind farm's two offshore high-voltage substations — Borssele Alpha and Borssele Beta — were built on jacket structures, a lattice design whose permanent-state engineering assumes a fully braced, piled, and grouted system. Getting there is a separate problem entirely.
Before piles are driven. Before grout locks the system. The jacket you see standing today spent most of its life as a completely different structure.
Borssele's substation jackets are a reminder that a structure's permanent design only describes one state among several it must survive. Load-out, transport, and upending each impose their own load cases — and getting a jacket safely through all of them, intact, is a distinct engineering problem from designing the structure it becomes once the piles are driven.
For further reading on temporary structural states, see What is Temporary Works & Erection Strategy?
Related case studies: London Array · Horns Rev 1 · Hywind Tampen
Sources: HSM Offshore Energy — EPCI contractor's record for the Alpha jacket and topside; Offshore Energy — Beta jacket and topside installation dates. This case study covers the two TenneT offshore high-voltage substations (Alpha and Beta), not the wind-farm turbine foundations.
Frequently Asked Questions
While the Borssele wind turbines themselves stand on monopile foundations, the wind farm's offshore high-voltage substations — Borssele Alpha and Borssele Beta — were built on four-legged jacket foundations, a lattice steel structure distinct from the single-pile monopile design used for the turbines.
During load-out, transport, upending, and pre-piling, a jacket experiences structural conditions it was never designed to see in service — horizontal transport loads, dynamic motions at sea, and the bending stresses of rotating from horizontal to vertical. Before piles are driven and grout locks the system into its final, braced configuration, the jacket must survive as a standalone structure under a completely different set of load cases than its permanent design addresses.
Upending is the controlled rotation of a jacket foundation from the horizontal orientation used for transport — typically on a barge or vessel deck — to the vertical orientation required for installation. It is usually performed using a crane, ballasted flotation, or a combination of both, and represents one of the highest-risk phases in the jacket's installation sequence.
Once upended and positioned, pin piles are driven through the jacket's legs into the seabed, and the connection is typically completed with grout, which locks the jacket into its final, fully braced structural system — the state its permanent design actually assumes.