Troll A stands 472 metres from the seabed to its topsides in 303 metres of water in the Norwegian Trench — the tallest structure ever moved by humans. The gravity-base structure (GBS) was built at Hinnavågen and Vats, Norway; the topsides at Aker Stord. In January 1995 the two units were mated inshore, in the deep-water fjord at Vats — the GBS partially submerged, the topsides floated in and set on top — before the complete, integrated platform made the passage north as one piece.

No offshore crane lift was used to install it. Troll A's installation is a case study in a different erection logic entirely: a single continuous tow governed by one seasonal weather window, followed by controlled ballasting and individually managed skirt-compartment pressure — doing the work a jack-up or heavy-lift vessel would do elsewhere.

472 m
Total height
~656,000 t
Dry weight (Guinness)
~683,600 t
Unballasted (Aker Solutions)
303 m
Water depth
36 m
Skirt penetration
10
Tugs, tow convoy
1995
Installed
Stage 1
Inshore construction and mating
The GBS was constructed at Hinnavågen and Vats; the topsides separately at Aker Stord. In January 1995 the two were mated in the fjord at Vats, producing one integrated platform ready for tow — roughly 245,000 m³ of concrete in the GBS alone, with ballast cells at the base to control final draft.
Stage 2
Tow-out inside a single seasonal weather window
The tow departed Vats on 10 May 1995: 10 tugs (8 pulling, 2 steering), transit at approximately 1 knot, roughly 200 km to the Troll field, with the majority of the structure's height — some 245 m — riding below the waterline. On 16 May the convoy was forced to stop: winds reached 40 knots, seas reached 5 metres, and all 10 vessels held position on charter, unable to shelter or return to Vats until conditions eased.
Stage 3
Ballasting and skirt penetration into soft clay
The platform reached location on 17 May 1995, roughly a week ahead of schedule. Controlled ballasting increased draft until the structure contacted the seabed; continued ballasting then transferred load progressively to the foundation as concrete skirts penetrated 36 metres into normally consolidated soft clay, with water pressure within individual skirt compartments managed to control penetration and levelling, confirmed at target elevation by approximately 19 May — set down without a single mooring line.
The commercial exposure behind the weather stop

The 16 May weather hold lasted hours, not days — but the charter clocks on all 10 vessels ran the entire time it lasted, and nobody in the convoy knew in advance how long that would be. The tow's physical dependency on a single seasonal window made that exposure impossible to miss; on programmes without a comparable physical constraint, the same daily-rate exposure often stays invisible to whoever controls the schedule.

Ten tugs, one weather window, and a structure too large to shelter or turn back — the convoy could not return to port, only hold position until conditions eased.

Troll A's installation logic has no direct equivalent among crane-lift or float-over methods: the structure was both the payload and the installation mechanism, with ballast control substituting for rigging and skirt penetration substituting for piling. First commercial gas followed on 1 October 1996; the Troll field holds roughly 40% of Norwegian Continental Shelf gas reserves.

For further reading, see Heavy Lift Engineering for Offshore & Marine Construction and Jacket Lift System Interfaces, which place Troll A's ballast-controlled installation alongside crane-lift and float-over methods used on other platforms.

Related case studies: Moho Nord · Tyra TEG Module Lift · Gullfaks C · Costa Concordia

Troll A — Tow Sequence and Weather Window Dependency

Troll A — tow sequence from Vats to Troll field, May 1995 Schematic showing the Troll A integrated platform (GBS and topsides pre-mated at Vats) towed 200 km to the Troll field in May 1995. Weather stop on 16 May: 40-knot winds, 5-metre seas. Platform arrived on location 17 May, approximately one week ahead of schedule. Seabed penetration completed approximately 19 May 1995. SEA SURFACE SEABED · 303 m WATER DEPTH · TROLL FIELD · NORWEGIAN NORTH SEA TOW UNDERWAY — 10–16 MAY 1995 WEATHER STOP — 16 MAY: 40 KT WINDS · 5 M SEAS Convoy holds position. 10 vessels on charter. Window running. TOPSIDES majority submerged TUG ×8 STEER ×2 40 KT WIND 5 m SEAS CONVOY HOLDS STANDBY EXPOSURE — WINDOW RUNNING [hold days] × [fleet charter rate] = exposure cannot return to shelter · cannot advance ON LOCATION — 17–19 MAY 1995 ARRIVED ~1 WEEK AHEAD OF SCHEDULE Ballasting complete · skirts penetrate seabed · window met TOPSIDES — MATED AT VATS JAN 1995 SKIRTS · SEABED PENETRATION FIRST GAS: 1 OCTOBER 1996 ~40% of Norwegian Continental Shelf gas reserves GBS in tow Standby / weather hold On location — window met EE&HL Network 2026
Diagram: Original — EE&HL Network 2026. First published in EE&HL Newsletter Issue 4, reused here for the case study.
Troll A concrete gravity-base platform standing in the North Sea at sunset, its four concrete legs rising from the water to the topside deck
The Condeep platform Troll A stands in 303 m of water in the North Sea and is 472 m tall overall.
Photo: Øyvind Knoph Askeland, Norsk olje og gass, CC BY-SA 2.0, via Wikimedia Commons.

Sources: Troll A platform — dimensions, tow-out chronology and the record framing. Note that Troll A is the tallest structure ever moved, not the heaviest: Gullfaks C carried the greater displacement. Published heights differ depending on whether the figure is measured from the seabed or from the waterline.