The Project
Gilberto Borja Navarrete Viaduct (formerly San Marcos Viaduct), Puebla, Mexico. Built 2009–2012; opened to traffic September 2014. Source: the design team's paper in Hormigón y Acero, 2015.
Figures: Arribas Mazarracín et al., Hormigón y Acero 66(275), 2015.
Work on the Gilberto Borja Navarrete Viaduct began in March 2009 with the foundations of its tallest pier. The viaduct, formerly the San Marcos Viaduct, carries the Nuevo Necaxa–Ávila Camacho section of the Mexico City–Tuxpan corridor across the San Marcos River valley in Puebla. Design and construction were awarded to CONNET, a joint venture of FCC Construcción and ICA.
The deck is 850 m long, with spans of 57, 98, 3×180, 98 and 57 m. Pier 4 stands 208 m above the valley floor; at the time of construction it was the tallest pier built in a balanced-cantilever bridge, according to the design team's paper.
Five piers stood on shallow footings. The sixth needed 64 piles.
This is not a story about the tallest pier. It is a commercial exposure created when an early-warning test runs after the batch it was meant to warn on.
Pier 4 sits on a meander of the San Marcos. Rock outcropped across one quarter of its footprint; the rest was alluvial sand and gravel to a depth of 20 m. The design called for 64 piles, 1.5 m in diameter, bored behind a temporary embankment. The embankment allowed work while river flow stayed below 1,000 m³/s, which gave a working season from December to May.
The design specified sonic testing as soon as the first few piles were cast, to catch problems in the construction procedure. A series of hindrances delayed the tests until all 64 piles were finished in July 2009. Only 14 piles (22%) were unaltered. Cores and a pile-by-pile recalculation then allowed 53% of the piles to be accepted. The paper says the cause of the defects could not be clearly established.
Piles with insufficient capacity were injected with grout. The work was suspended when the river rose and finished in March 2010, but it did not repair enough piles for the foundation to perform as required. In May 2010 a reinforcement of 14 further piles was designed, 1.20 m in diameter and cased throughout. They were completed in June 2010.
The 34 m × 34 m pile cap, 6,000 m³, was then cast continuously over four days, with ice flakes replacing part of the mixing water, so that shaft work could start before seasonal flooding.
The paper states that the pier 4 deck conditioned construction time. That deck was completed in September 2012, the main structure in November 2012, and the section opened to traffic in September 2014.
⚙️ Pier 4 foundation — before and after strengthening
Schematic, not to scale; sections show representative piles and count strips show totals, not locations. Exposure formula is illustrative. Diagram: Original — EE&HL Network 2026 · Tap or click the diagram to open it full size.
⚙️ Pier 4 Foundation — Sequence (Published Record)
- Mar 2009 — Pier 4 foundation works begin, behind a temporary embankment.
- Jul 2009 — All 64 piles complete. Sonic tests run: 14 unaltered (22%).
- Then — Cores and pile-by-pile recalculation: 53% of piles accepted.
- Mar 2010 — Grout injection finished, after a suspension when the river rose. Not enough piles repaired.
- May 2010 — Reinforcement of 14 supplementary piles designed.
- Jun 2010 — Supplementary piles completed.
- Then — Pile cap cast continuously over four days.
- Sep 2012 — Pier 4 deck completed.
- Nov 2012 — Main structure completed.
- Sep 2014 — Section opened to traffic.
The Pattern & The Question
What changes when an early-warning test reports after the whole batch, an illustrative exposure framework, and three questions to put to your own test sequence.
Sections 2 and 3 are delivered free by email. Subscribe below and they land in your inbox now.
Subscribe Free — Get the Full Issue →Free. No card required. Unsubscribe any time.
Sources and further reading
- Design teamArribas Mazarracín, D., González Esteban, J. I., Pérez Casas, J. M. and Bernal Sahún, P., “Gilberto Borja Navarrete Viaduct”, Hormigón y Acero 66(275), 2015 (English edition)Source: geometry, pier 4 foundation, sonic test results, grouting, supplementary piles, pile cap, deck completion and opening dates. Spanish edition.
- PhotoHighestBridges, Wikimedia CommonsCC BY-SA 3.0.
Source labels describe provenance, not authority. See our editorial methodology.
Marco Torri
Founder and Editor, EE&HL Network · Commercial intelligence for erection engineering & heavy lift