When Deepwater Wind set out to build America's first commercial offshore wind farm, no domestic manufacturer could supply the monopile foundations Europe had standardised on. European offshore wind contractors, meanwhile, were waiting to see whether a US market would materialise before committing resources of their own.
The answer engineers reached for wasn't a new foundation type — it was an old one, borrowed from a different industry entirely. Four-pile jacket foundations, developed for offshore oil and gas platforms, were adapted for wind turbines and built using expertise the US Gulf Coast already had in abundance.
No domestic monopile supply chain existed yet, so the industry didn't wait to build one — it borrowed a proven foundation type from offshore oil and gas instead.
Block Island Wind Farm became fully operational in December 2016, the first commercial offshore wind farm in the United States. As a reference case, it shows how an entire new industry segment got its start not through novel technology, but through the deliberate reuse of proven offshore engineering from an adjacent sector — jacket foundations, Gulf Coast fabrication, and marine installation expertise, all repurposed for wind.
For further reading on offshore wind foundation methods, see Offshore Wind Sector Hub
Related case studies: Horns Rev 1 · Vindeby · Borssele
Sources: Weeks Marine — installation contractor account of jacket transport, pile driving, welding and grouting; Manson Construction — joint-venture project record for the five 400-ton jacket foundations; Keystone Engineering — designer's account of the four-pile jacket substructures; Tethys (Pacific Northwest National Laboratory) — project status, capacity, foundation type and commercial-operation date.
Frequently Asked Questions
At the time of development, Europe had built many offshore wind farms predominantly using monopile foundations, but that manufacturing capability did not exist in the United States, and European firms were waiting to see how the US offshore wind industry developed before becoming engaged. Engineers instead adapted a four-pile jacket foundation design from offshore oil and gas platform technology, which US suppliers could fabricate.
The jacket foundations were designed by Keystone Engineering and fabricated by Gulf Island Fabrication in Louisiana, a company experienced with oil and gas platforms but new to wind. A joint venture between Weeks Marine and Manson Construction served as the offshore foundation installation contractor.
Each jacket was semi-submerged with its topside rising between 20 and 95 feet above the water, then secured with four 300-foot-long piles driven into the seabed at each corner, with the pile tops welded and grouted to complete the connection.
Waves averaging over 3 ft challenged the project's floating rigs during pile driving. To keep the schedule on track, the installation team brought in an additional lift boat carrying a 500-tonne crane as a subcontractor — a vessel normally used for decommissioning offshore oil and gas platforms — to support the majority of the pile-driving work.