The Beijing National Stadium, known as the Bird’s Nest, hosted the opening ceremony of the 2008 Olympic Games on 8 August 2008. Herzog & de Meuron designed it with the China Architecture Design & Research Group, Arup was structural engineer, and Beijing Urban Construction Group was general contractor. Groundbreaking was in December 2003.
Its outer structure is a steel lattice of about 42,000 t of twisted, non-repetitive box-section members, carried on 24 trussed columns of roughly 1,000 t each. Temporary supports carried the primary roof structure through assembly and closure, before its load was transferred into the permanent structure. The project paper describes unloading a roof of about 14,000 t; the 42,000 t figure covers the wider outer steel structure. Secondary top-surface steel was installed after the primary structure had been unloaded, so the erection scheme was as much a plan for taking the supports away as for putting them up.

Sources: Li et al., CIB W78 (2013); China Daily (18 September 2006); Enerpac (2007). Diagram: EE&HL Network, 2026.
The temporary works at the Bird’s Nest did not end with the last closure weld. They ended when 156 jacks had lowered the roof onto the permanent structure and the measurements matched the calculation.
This is the moment the de-propping pages describe in general terms: load leaves the temporary supports and the permanent structure takes it up, through intermediate states. At the Bird’s Nest those states were planned in 35 sub-steps and measured as they happened. The sources reviewed describe the sequence and the result; they do not describe how responsibility for the unloading was allocated between the parties.
For the general pattern, see What Is a De-Propping Sequence? and the insight Why Removing Temporary Works Can Be Riskier Than Installing Them. For other roofs released onto themselves, see the Singapore Sports Hub and SoFi Stadium Canopy case studies, and for the closure constraint, Newsletter Issue 7.
Related case studies: Singapore Sports Hub · SoFi Stadium Canopy · Grande Arche · Eiffel Tower · Gateway Arch
Core concepts: What is erection engineering? · What is heavy lift engineering?

Photo: 东林 (Dong Lin), via Wikimedia Commons, CC BY 2.5 CN.
Sources: Li et al. — “National Stadium (Bird’s Nest) Digital Construction Technology”, CIB W78 2013 — steel tonnage, 78 supports, unloading steps, 286 mm and 271 mm, closure dates, monitoring points, general contractor; China Daily — 18 September 2006 — 24/24/30 distribution of the 78 supports, 35 mini-steps in seven phases, jacking pads; Manufacturing.net — “Beijing’s Bird’s Nest becomes permanent”, March 2007 — the 156 hydraulic cylinders and the lift, cut and lower procedure; The Structural Engineer — Fan, Z., “Design of large-span steel structure for the National Stadium, Beijing”, vol. 85, no. 22, 2007 — design context; Wikipedia — design team, groundbreaking and the 24 trussed columns. Steel tonnages quoted for the stadium differ between sources because they cover different scopes; the 42,000 t figure is the outer steel structure as given in the engineering account, which puts the roof unloaded from the 78 supports at about 14,000 t. The two Newsletter Issue 7 constraints (closure temperature and window) are covered there and are not repeated in full here.
Frequently Asked Questions
78, according to China Daily and the engineering account: 24 along the outer circle, 24 in the middle circle and 30 in the inner circle.
In seven major steps and 35 sub-steps, using hydraulic jacks. The primary roof structure, about 14,000 t, was lifted synchronously off its supports, the welds were cut and it was lowered in stages. The engineering account counts 156 jacks. Secondary top-surface steel was installed after unloading.
The calculated maximum deformation on unloading was 286 mm and the measured value was 271 mm, a difference of 5.2%.
The outer steel structure is reported at about 42,000 t. The roof carried on the 78 temporary supports and then unloaded is put at about 14,000 t in the project paper. Other totals quoted for the stadium cover different scopes, so a figure should be read together with what it includes.