At the ITER facility in southern France, engineers are assembling the vacuum vessel of the world's largest fusion reactor from nine wedge-shaped sector modules, each weighing up to 1,200 tonnes — heavier than a fully loaded jumbo jet.

Each module is lowered into the tokamak assembly pit through a gap of well under a metre — ITER Organization's own figures put the usable margin at under 20 centimetres at the tightest point. It is a heavy lift and a nuclear-grade precision problem occurring simultaneously, with almost no room to correct mid-descent.

up to 1,200t
Per sector module
<20 cm
Vertical clearance
9
Sector modules total
~8,500t
Vessel once fitted out
Stage 1
Sub-assembly
Each sector module is built up in purpose-built sub-assembly tooling — towers roughly 22 metres high and weighing several hundred tonnes — combining a vacuum vessel sector, thermal shielding, and two D-shaped superconducting toroidal field coils before ever entering the pit.
Stage 2
Upending and transfer
The completed module is upended from horizontal to vertical using a dedicated tool, lifted by overhead crane, and transported across the Assembly Hall to the wall separating it from the machine assembly pit.
Stage 3
Descent and alignment
The module is lowered into the pit under continuous metrology, with specialists tracking the descent in real time through a clearance margin of less than 20 centimetres, before positioning with sub-millimetric precision on its supports.
Clearance note

ITER's own account of the first sector module lift describes vertical clearance during transfer as not exceeding 20 centimetres, tightening further during final descent. At a scale where the module is the size of a five-storey building, that margin leaves essentially no tolerance for error.

A component the size of a five-storey building, lowered through a gap of less than 20 centimetres — nuclear-grade tolerance applied at heavy-lift scale.

The full vacuum vessel, once its nine sectors are welded together, will weigh approximately 5,200 tonnes; with in-vessel components installed, that rises to roughly 8,500 tonnes. ITER's own engineers describe the assembly as combining nuclear-grade quality constraints with clearances and component geometries that have no direct precedent elsewhere — lessons with relevance well beyond fusion energy.

For further reading, see Erection Engineering for Industrial Construction, which places confined-clearance precision lifting in a wider sector context.